What you can do
Open any System & Equipment record and use the Integration tab.
File a document
Pick what kind of document it is, then upload the file. Citiri puts it in that facility’s document library, in the matching folder, and saves a link you can share.
The choices are Commissioning, Drawings, an Operations and Maintenance manual, Warranty, and Other.
If you upload a newer version of the same kind, the new file takes its place. The older file is kept under Other, and its old link stops working.
Send the links to Cityworks
When the documents are in, Publish to GIS sends their links to the matching asset in Cityworks. The panel shows the Cityworks number, the kind of asset, and whether there is anything ready to send.
Citiri only sends the links when it can match exactly one asset. If it cannot, nothing in Cityworks is changed, and the attempt is recorded so you can see why.
What you will see on the tab
- Upload Asset Documents is where you choose the document type and add the file.
- Asset Documents lists every file filed for this asset, with its type and its link.
- Publish documentation to GIS is the button that sends the links, and it tells you the result.
- GIS Doc Push Logs is the history of each send: whether it went through, and what came back.
Photos stay in the Images tab. Documents filed here stay in the document library, so the two do not get mixed together.
Maintenance Building 8
The building and eight pieces of equipment are ready to use. Each one already knows its Cityworks number.
| Asset | Cityworks number | Kind | |
|---|---|---|---|
| Maintenance Building 8 | — | Facility | Open |
| Panel 0554 | 0554 | Panel | Open |
| Panel 2501 | 2501 | Panel | Open |
| Generator 2504 | 2504 | Generator | Open |
| Switch Auto Transfer 2524 | 2524 | Switch | Open |
| Transformers 2499 | 2499 | Transformer | Open |
| Mini Split 2512 | 2512 | Mini split | Open |
| Unit Heater 2521 | 2521 | Unit heater | Open |
| Overhead Door 2497 | 2497 | Overhead door | Open |
Open one of these, go to the Integration tab, and the upload and publish tools are on that page. Sending a link updates the live Cityworks record, so check with the GIS team before you publish a real document.
Where the files go
Each facility has its own document library. Equipment that belongs to that facility uses the same library. Maintenance Building 8 uses the library that was already set up for it.
Every library has the same five folders:
- Commissioning and test reports
- Drawings
- Operations and maintenance manuals
- Warranties
- Other
When a new facility is added in Citiri, its library and these folders are created for it. The Cityworks list of asset types is connected, so a link can be sent for each kind except the few noted at the bottom of this page.
Other facilities
These already have a document library. Equipment filed under one of them uses that library. Open any of them and use the Integration tab the same way as Maintenance Building 8. None of these have a Cityworks number yet, so a link cannot be sent until that number is added.
| Facility | |
|---|---|
| 11 - Equipment Systems | Open |
| 14 - Conveying Equipment | Open |
| 21 - Fire Suppression | Open |
| 22 - Plumbing | Open |
| 23 - HVAC Systems | Open |
| 26 - Electrical Systems | Open |
| 27 - Communication Systems | Open |
| 28 - Electronic Safety and Security Systems | Open |
| 31 - Earthwork | Open |
| 32 - Exterior Improvements | Open |
| Electric Radiant Heaters | Open |
| HVAC | Open |
Reports and history
Two reports show what has been filed, and one list shows every time a link was sent to Cityworks.
Who can use it
Jamie Timmons and Juan Coleman can manage every facility document library and share it with other people. Shelley Lamar, Shironika Farrior, Tracy Adkison, and Toni Jackson can do the same. Aaron Davis can open the files in each of those libraries.
The Citiri administrators can use the upload and publish tools as well.
What is still open
- Lighting circuit points and property fences cannot receive a document link. Cityworks does not keep an ID on those, so there is nothing to match.
- Other mechanical equipment has no document list in Cityworks, so commissioning and drawing links for that kind cannot be sent.
- Only the eight Maintenance Building 8 assets have a Cityworks number on the record. Documents can still be filed for other equipment. Sending the link waits until the Cityworks number and the kind of asset are added.